Development Time for MEEPS ECPE 5




























Task
Estimated Actual
Error
Assembly + Purchasing

1.9 5.6% -1.9
Code

2.5 7.2% -2.5
Debug/Test

1.8 5.2% -1.8
Design
2 2.5 7.3% -0.5
Documentation
2 6.1 17.7% -4.1
PCB Layout
4 3.6 10.4% 0.4
Project Admin
2 4.6 13.5% -2.6
Research
2 0.3 0.8% 1.7
Specifications
1 1.4 4.2% -0.4
Travel

6.0 17.4% -6.0
Update web site

3.7 10.8% -3.7
Total Time (hrs):
13.0 34.5 100.0% -21.5







Date Project Name Task Start Time End Time Net Hours Note
02/06/04 MEEP - ECPE 5, 2004 Assembly + purchasing 11:14:00 12:55:00 1.7 Build 1st board, CPU
02/06/04 MEEP - ECPE 5, 2004 Assembly + purchasing 13:59:00 14:15:00 0.3 1st build - display board
02/23/04 MEEP - ECPE 5, 2004 Code 14:40:00 19:50:00 2.5 Get matrix test running on 18F452, including email to Dick after I found the RA4 problem
02/23/04 MEEP - ECPE 5, 2004 Debug/Test 12:00:00 14:27:00 1.8 Debug Dick's Matrix program
01/16/04 MEEP - ECPE 5, 2004 Design 08:38:00 09:44:00 0.8 Consider PWR options Cap values are correct for MAX3232, MAX232A, but not MAX232 (no A)
01/16/04 MEEP - ECPE 5, 2004 Design 11:29:00 15:42:00 1.1 1.0uf cap selection, mods to schematic and BOM
01/16/04 MEEP - ECPE 5, 2004 Design 15:42:00 16:39:00 0.7 Clean-up BOM
02/24/04 MEEP - ECPE 5, 2004 Documentation 13:51:00 22:45:00 3.8 Preparing Lecture
02/25/04 MEEP - ECPE 5, 2004 Documentation 08:05:00 13:36:00 2.3 Prep for talk to ECPE5 class
01/15/04 MEEP - ECPE 5, 2004 PCB Layout 09:02:00 09:47:00 0.8 Correct pot on DISPLAY
01/16/04 MEEP - ECPE 5, 2004 PCB Layout 10:42:00 12:04:00 0.9 Figure out pads for 1N4001
01/20/04 MEEP - ECPE 5, 2004 PCB Layout 19:42:00 22:02:00 1.9 CPU and DISPLAY combination
01/14/04 MEEP - ECPE 5, 2004 Project Admin 16:44:00 17:30:00 0.3 Review old project to make estimates
01/20/04 MEEP - ECPE 5, 2004 Project Admin 21:11:00 21:26:00 0.3 PCB Cost est from PCB123
01/20/04 MEEP - ECPE 5, 2004 Project Admin 22:02:00 22:37:00 0.6 Email report to Dick
01/22/04 MEEP - ECPE 5, 2004 Project Admin 09:48:00 10:01:00 0.2 Phone call to discuss order with Dick. Email with qty to follow
02/06/04 MEEP - ECPE 5, 2004 Project Admin 14:33:00 15:06:00 0.6 Deal with bad boards - 16 of 50 800 228 8198 x236
02/23/04 MEEP - ECPE 5, 2004 Project Admin 11:25:00 11:55:00 0.5 Setup devel sys
02/23/04 MEEP - ECPE 5, 2004 Project Admin 14:27:00 14:40:00 0.2 Reinstall compiler
02/25/04 MEEP - ECPE 5, 2004 Project Admin 15:22:00 15:42:00 0.3 Clean up directories and make sure all files are up-to-date
02/26/04 MEEP - ECPE 5, 2004 Project Admin 10:00:00 11:45:00 1.8 Presentation to the ECPE 5 class
01/14/04 MEEP - ECPE 5, 2004 Research 17:24:00 17:40:00 0.3 Can spreadsheets be moved to OpenOffice
01/14/04 MEEP - ECPE 5, 2004 Specification/Analysis 17:10:00 19:02:00 0.2 Preliminary specs to make time estimates - created file MEEPS_ECPE5_2004.txt
01/15/04 MEEP - ECPE 5, 2004 Specification/Analysis 20:38:00 21:19:00 0.7
01/16/04 MEEP - ECPE 5, 2004 Specification/Analysis 09:25:00 11:29:00 0.6 Phone discussion with Dick
02/06/04 MEEP - ECPE 5, 2004 Travel 08:30:00 10:00:00 1.5 Drive to UOP
02/06/04 MEEP - ECPE 5, 2004 Travel 19:30:00 21:00:00 1.5 Return from Stockton, 87miles
02/26/04 MEEP - ECPE 5, 2004 Travel 08:00:00 09:30:00 1.5 To Stockton, 87miles, for ECPE 5 Lecture
02/26/04 MEEP - ECPE 5, 2004 Travel 19:00:00 20:30:00 1.5 From Stockton, 87miles, for ECPE 5 Lecture
02/25/04 MEEP - ECPE 5, 2004 Update web site 20:30:00 22:00:00 1.5
02/27/04 MEEP - ECPE 5, 2004 Update web site 13:51:00 16:05:00 2.2

























Total = 34.5